UK Power Networks budgets £12m for DSR, reduces entry size to 50kW

0
Sotiris Georgiopoulos: If you have flex, we’d like to hear from you

UK Power Networks has allocated £12 million to buy demand-side response to help manage its grids in southeast and east England.

The DNO has also extended the deadline for companies that want to participate in its next round of procurement, and reduced the minimum capacity threshold to 50kW in a bid to drive greater uptake.

Those that can provide generation of load forms of response must register by 12 March to take part. Service delivery will start from winter 2019 onwards.

Last summer UKPN indicated it could require more than 200MW of demand-side response to defer load related reinforcement over the next four years. Now the DNO needs people that can provide flexibility where it is needed to come forward.

“It is early days for the flexibility market, but we’re fully committed to it. The sums we’re investing will ultimately save customers money by extending the life of our existing infrastructure,” said UKPN head of smart grid development Sotiris Georgiopoulos.

“Could you reduce your consumption or increase generation on instruction at peak times? If so and you’re a generator or developer with assets in any of our 28 locations, or if you can install new assets by winter 2020-21, then we’d be really happy to speak to you about how you can take part.

Piclo, an online platform that matches buyers of flex with assets in the right locations, will run the auction. The 28 locations where UKPN requires flexibility can be found on the Piclo site.

Businesses can register interest via flexibility@ukpowernetworks.co.uk. There are also more details here.

Meanwhile, the deadline to register assets for Northern Powergrid’s flexibility procurement, also via the Piclo platform, is currently midday 25 February. Details here.

WPD will issue a tender for 93MW of DSR next month.

Related stories:

Piclo eyes big 2019 as DNO flex deadlines loom

WPD to tender for 93MW of DSR

All DNOs commit to considering flexibility over network reinforcement

Northern Powergrid launches DSR tender

WPD extends Midlands and South West DSR call until 21 December

DNO flex procurement: The learning so far from UKPN and WPD

Aggregators: Upload your data to grow DNO flexibility markets

UKPN eyes 200MW of demand-side response, details new tenders

WPD to launch flexibility tenders across all networks in 2019

SPEN joins Piclo flex platform

Electricity North West signs up to Piclo platform, plans 36MW DSR tender

UK Power Networks partners with Open Utility on flex trial

SSEN to trial Open Utilities flex procurement platform

Local grids for local people

Click here to see if you qualify for a free subscription to the print edition of The Energyst, or to renew.

Follow us at @EnergystMedia. For regular bulletins, sign up for the free newsletter.

LEAVE A REPLY

Please enter your comment!
Please enter your name here