Ofgem investigates capacity market contracts over consent issues

0

800px-3D_Judges_GavelOfgem has opened investigations into five companies which secured contracts in last year’s capacity auction.

The regulator’s investigation centres on whether the companies have all necessary planning consents for proposed generators allocated contracts in the so-called t-4 auction in December.

The capacity market, which operates via auctions, is designed to reward generators for making plant available when it is needed and bring forward investment in new plant.

The first capacity auction (so-called T-4 because it secures capacity to be supplied in four years’ time) took place just before Christmas. It procured 49.26GW of capacity at a clearing price of £19.40kW.

Ofgem said today that it was investigating whether GF Power Peaking Ltd, Berangere Ltd, Adret Ltd, Alkane Energy UK and Power Balancing Service Ltd provided false or misleading information to National Grid, which runs the annual capacity auction.

The regulator said that the investigations did not imply that it had made any findings about non-compliance, but cited potential issues around planning consents in each case.

Decc tenders contract to scope DSR potential in future capacity auctions

Decc to pay firms for implementing energy efficiency projects

UK firms with CHP plant could be paid to stop exporting power

More money for CFD generators

CFD appeals may cost ineligible generators, Decc warns

Energy minister dismisses big company bias claims from renewable energy groups in capacity and CFD auctions

UK businesses pan electricity market reforms, prepare for 10% power price hikes in 2015

Another fine mess: Energy policy’s perverse outcomes mean ‘new Energy Act by 2017′

Click here to see if you qualify for a free subscription to the print magazine, or to renew.

Follow us at @EnergystMedia. For regular bulletins, sign up for the free newsletter.

 

LEAVE A REPLY

Please enter your comment!
Please enter your name here