developer Archives - theenergyst.com https://theenergyst.com/tag/developer/ Thu, 08 Feb 2024 14:07:08 +0000 en-GB hourly 1 https://wordpress.org/?v=6.5.3 https://theenergyst.com/wp-content/uploads/2020/10/cropped-TE-gravatar-2-32x32.png developer Archives - theenergyst.com https://theenergyst.com/tag/developer/ 32 32 MPs to hear solar developers’ complaints over NG’s and DNOs’ ‘farcical’ hook-up waits https://theenergyst.com/mps-to-hear-solar-developers-complaints-over-farcical-hook-up-waits/ https://theenergyst.com/mps-to-hear-solar-developers-complaints-over-farcical-hook-up-waits/#comments Wed, 07 Feb 2024 10:19:24 +0000 https://theenergyst.com/?p=20954 Leaders of Britain’s solar developers will meet two influential Parliamentary committees this afternoon, battling to shorten ‘farcical’ delays in connecting new batteries and PV farms. Too often, say industry representatives, such waits now stretch into the 2040s. One regional distribution operator, Northern Powergrid, has been accused of foot-dragging on a grid connection, after being unable […]

The post MPs to hear solar developers’ complaints over NG’s and DNOs’ ‘farcical’ hook-up waits appeared first on theenergyst.com.

]]>
Leaders of Britain’s solar developers will meet two influential Parliamentary committees this afternoon, battling to shorten ‘farcical’ delays in connecting new batteries and PV farms. Too often, say industry representatives, such waits now stretch into the 2040s.

One regional distribution operator, Northern Powergrid, has been accused of foot-dragging on a grid connection, after being unable to improve on a twelve-year wait to hook up one developer’s battery project.

Solar park builder Enviromena has taken the unusual step of issuing a public statement, accusing the DNO of “stifling” investment. The developer accuses Northern Powergrid of jeopardising the viability of its unbuilt farm at West Sleekburn, Northumberland.

Enviromena says its 30MW battery addition to the plant received planners’ approval in October 2022. But after talks, the DNO now can guarantee no grid connection date for the intended battery before October 2036.

According to the developer, Northern Powergrid indicated in discussions last year that its grid supply point at Blyth might enable an earlier connection, possibly available under the DNO’s Delegated Technical Limits programme.

The developer had hoped to confirm that earlier connection date before Christmas. But Northern Powergrid later told it that the Blyth hub had been removed from the DNO’s programme of accelerated connections, due to technical reasons. The developer says the grid company can commit to no alternative before the already stated deadline twelve years from now.

Enviromena CEO’s Chris Marsh said in a statement: “We are extremely disappointed with the latest delay, which has left a key project without a feasible connection date despite being ready to construct.

“The North East is enjoying a renaissance for clean energy as it emerges as a key hub for renewables, Marsh went on.

“The actions of Northern Powergrid go directly against the Government’s wider agenda to move away from fossil fuels and achieve carbon Net Zero goals by 2050 and it is stifling investment in the area. The delay represents a major setback.”

He added: “We submitted details to Northern Powergrid demonstrating our West Sleekburn project was ready for an earlier connection with both planning and land rights in place.

“The site is ready to provide much-needed storage facilities for cleaner energy. I would urge Northern Powergrid to re-focus their efforts on resolving the issues at Blyth and kickstarting accelerated connections in the area.

“We have seen other network operators across the country accelerate connection dates by as much as thirteen years in recent weeks and we hope a similar resolution can be found for the Sleekburn project.”.

Marsh cited the National Grid’s estimates that Britain will need over 25GW of battery storage, up from 1GW today, if it is to decarbonise the nation’s grid by 2035.

Reading-based Enviromena last month announced it was about to submit a total of 400MWp new unbuilt PV farm proposals for planners’ consideration, en route to an intended 500MWp goal next year.

Responding in a statement, Northern Powergrid confirmed the developer’s account.  The operator said it was working hard to bring forward connection dates for customers with schemes delayed by constraints on the transmission network owned and operated by National Grid.

The DNO commented: “Towards the end of last year, we announced that we would be issuing revised connections offers for some customers, made possible through a programme of delegated technical limits”.

“Customers looking to connect at a major substation at Blyth in Northumberland were included in the proposal for the first phase of this work.

“However, after further scrutiny by ourselves and National Grid, it will not be possible during this stage of the programme and so we’re re-evaluating what we can do to support customers looking to connect to this area of our network.

“We remain committed to working with our customers whose projects are impacted and to keeping them informed about the actions we are taking to accelerate grid connections in our region”.

This afternoon trade body SolarEnergyUK will present to MPs evidence of what it calls connection delays ‘descending into farce’.  Queues to connect to the grid, at both low and high voltage, now surpass 500GW, the group claims, citing a recent estimate by consultancy Roadnight Taylor.

Reforms such as the ‘Technical Limits’ programme, intended to deliver connections for big batteries and generating assets in advance of reinforcements to the transmission grid, would only be possible if output from the new supply assets was cut at source, DNOs have told Solar Energy UK said.

The most permissive limit seen by the body is 63%, in return for a connection date being brought forward by a year. In some cases, said the group, developers have been told that this limit is zero, with not a single solar-powered electron being allowed to flow.

Grid consultancy Novogrid has seen 50 such messages over the past three months, all with curtailment above 90%.

“You couldn’t make it up“, said SolarEnergy UK CEO Chris Hewett. “It is like being told you can open a shop on the High Street, as long as you keep the doors locked.

“This is bizarre behaviour“,  he added, “an apparent attempt by the DNOs to make it look like they are doing something while they still fail to invest in vital upgrades.”

Hewett will present this afternoon to the Commons’ environmental audit committee.  On the same topic also this afternoon, grid commissioner Nick Winser will answer MPs on the committee shadowing the D-ESNZ ministry.  Coverage begins at 14:00; click on the links to view a live TV feed.

The post MPs to hear solar developers’ complaints over NG’s and DNOs’ ‘farcical’ hook-up waits appeared first on theenergyst.com.

]]>
https://theenergyst.com/mps-to-hear-solar-developers-complaints-over-farcical-hook-up-waits/feed/ 3
Smart phoning: Vodafone dials into 5 solar farms, as domestic on-roof PV instals double https://theenergyst.com/smart-phoning-vodafone-dials-into-5-solar-farms-as-domestic-on-roof-pv-instals-double/ https://theenergyst.com/smart-phoning-vodafone-dials-into-5-solar-farms-as-domestic-on-roof-pv-instals-double/#respond Wed, 22 Feb 2023 14:58:24 +0000 https://theenergyst.com/?p=18984 Mobile telecoms giant Vodafone has reached agreement with Centrica and solar developer Mytilineos to fund five new PV farms, capable of providing it with 216 GWH of low-carbon power. The trio’s PPA, their second struck in twelve months, will fund the Greek-based developer’s construction of five consented farms from Dorset to Nottinghamshire.   Construction is due […]

The post Smart phoning: Vodafone dials into 5 solar farms, as domestic on-roof PV instals double appeared first on theenergyst.com.

]]>
Mobile telecoms giant Vodafone has reached agreement with Centrica and solar developer Mytilineos to fund five new PV farms, capable of providing it with 216 GWH of low-carbon power.

The trio’s PPA, their second struck in twelve months, will fund the Greek-based developer’s construction of five consented farms from Dorset to Nottinghamshire.   Construction is due to be completed by early next year.

As offtaker, Centrica will sell a ‘significant’ proportion of their output to Vodafone, speeding the company towards its target of sourcing 44% of its power by 2025 from UK-based green sources. The remainder will be traded by the energy company.

Celebrating its customer’s underpinning of the new farms’ funding, Centrica chief executive Chris O’Shea, pictured, said: “The deal gives Vodafone UK access to clean, high quality and affordable renewable electricity for the next ten years, offering price certainty and improved energy security”.

Already in the UK 100% of the grid electricity which Vodafone uses is from certified renewable sources, the Centrica boss noted.

In May the trio signed a PPA by which Centrica would sell the phone company 109 GWh from three new solar farms in the Midlands, totalling 110 MWp in capacity.  The first is now generating, with the rest soon to follow.  Along with two onshore wind farms in Northamptonshire and Lincolnshire, Vodafone UK now has dedicated access to renewable power from 10 sites across the UK.

The supply deal was announced as industry body SolarEnergyUK confirmed today that no longer subsidised instals of rooftop solar PV, overwhelmingly on homes and all under 50kWp in potential, doubled in 2022 on 2021’s figures.

Confirming figures from technical standards overseer the MCS, the solar lobbyists said over 130,000 roofs received new solar arrays last year, almost equalling completions for the previous two years combined.

Last month’s fixing of 16,043 new systems under 50kWp potential was three times the total for January 2022, setting a new monthly record for volumes of subsidy-free installations.

“Solar is surely one of the fastest-growing sectors in the UK right now”, said the lobbyists’ CEO Chris Hewett. “The rapid increase in sales is great news for the economy, public pockets, Net Zero and of course for energy security too”,

But he warned that even the current pace of installation must double again for consumer-scale systems to match the government’s target set for all solar power in its Energy Security Strategy published in April.

Even that heightened target is “clearly achievable”, Hewett advised, since it would be less than levels achieved in 2011 and 2012, at the height of the Feed-in Tariff era.

The post Smart phoning: Vodafone dials into 5 solar farms, as domestic on-roof PV instals double appeared first on theenergyst.com.

]]>
https://theenergyst.com/smart-phoning-vodafone-dials-into-5-solar-farms-as-domestic-on-roof-pv-instals-double/feed/ 0